Background of the Case
The petitioners, Deepak Bareja and another, owned land in Village Bhuppur-II, Tehsil Paonta Sahib, District Sirmaur, Himachal Pradesh, which was acquired for the widening and four-laning of National Highway No. 72 (Paonta Sahib–Ballupur).
The Competent Authority for Land Acquisition passed Award No. 3/2022 on February 14, 2022, determining compensation payable to the petitioners at ₹3,78,76,160.
However, the authorities deposited the compensation amount with the Competent Authority only on February 16, 2023, resulting in a delay of 367 days. Even after the deposit, the amount was withheld pursuant to administrative instructions pending arbitration proceedings challenging the award.
During the pendency of the writ petition, the petitioners received the compensation and confined their claim to interest for the delay.
Arguments of the Parties
The petitioners contended that they were entitled to interest for the period between the passing of the award and the deposit of compensation, as the award had not been stayed during that period.
The authorities argued that the compensation was withheld because of pending arbitration proceedings. They also contended that the petitioners had delayed handing over possession of the acquired land, affecting the construction of the highway.
Court's Observations
Justice Sandeep Sharma observed that under Section 3D(2) of the National Highways Act, 1956, land vests absolutely in the Central Government upon publication of the acquisition declaration, free from all encumbrances. Therefore, the alleged delay in handing over possession could not justify denying interest to the petitioners.
The Court further examined Sections 3G and 3H of the Act. It observed that Section 3H(1) requires the Central Government to deposit the compensation determined under Section 3G with the Competent Authority before taking possession of the acquired land. Under Section 3H(2), the Competent Authority must pay the deposited amount to the persons entitled to receive it.
The Court also held that administrative instructions issued by the authorities could not override the statutory obligation to release compensation after the award.
Observing that no stay order was in operation during the relevant period, the Court held:
"Since there was a delay in deposit of award amount for one year and during afore period, no stay order by any competent court of law was passed, petitioners ought to have been released amount of compensation alongwith interest for the period with effect from 15.2.2022 to 16.2.2023."
Final Decision
The High Court allowed the writ petition and directed the authorities to pay interest at 7.5% per annum on the compensation payable to the petitioners for the period from February 14, 2022, to February 16, 2023.
The amount was directed to be deposited with the Competent Authority within two weeks for release to the petitioners. The Court further directed that failure to deposit the amount within the stipulated period would attract enhanced interest at 18% per annum from the date of the order until actual payment.
Case Details
Case Name: Deepak Bareja and Another v. Union of India and Others
Court: Himachal Pradesh High Court
Date of Decision: 05.10.2026
Case Number: CWP No. 2816 of 2024
Coram/Judge: Justice Sandeep Sharma