Background of the Case

M/s Marino Dredgeco Limited was engaged by the Board of Trustees of the Port of Kolkata to undertake dredging work at Sagar Island for a shore-based pilot station. Although the original work was completed, repeated siltation necessitated additional dredging. The Port Trust had entrusted the additional work through a letter dated 19 July 2000.

The contractor attributed the additional work to adverse weather conditions, incorrect soil data supplied by the Port Trust and the absence of protective walls.

The arbitral award dated 3 November 2003 determined the amounts payable for the additional work. The award was upheld by a Single Judge of the Calcutta High Court under Section 34 of the Arbitration and Conciliation Act, 1996.

However, the Division Bench, exercising jurisdiction under Section 37, reduced the awarded amount by 50% and lowered the interest rate to 6%. It reasoned that the additional work claims exceeded 70% of the original contract value, thereby shocking the Court's conscience.

Supreme Court's Observations

The Supreme Court found that the High Court had interfered with the award without identifying any legally sustainable ground for doing so.

It observed that the additional work involved re-dredging, which was essentially similar to the original dredging work. The arbitrator had relied upon measurements, invoices and pre-work and post-work levels to determine the amount payable. Even the High Court had acknowledged that the award was supported by adequate evidence and was neither perverse nor patently illegal.

Referring to Ssangyong Engineering & Construction Co. Ltd. v. NHAI, the Court emphasised that an award can be considered contrary to the basic notions of morality or justice only when there is a substantive reason demonstrating such conflict.

The Court observed:

"The words are not to be applied on a mere lip service and there should be a substantive reason which blatantly and patently brings forth the conflict with the most basic notions of morality or justice, resulting in the conscience of the Court being shocked."

Limited Powers of Courts Under Section 37

Relying on Somdatt Builders–NCC–NEC (JV) v. NHAI, the Bench reiterated that courts exercising jurisdiction under Section 37 cannot interfere with arbitral awards merely by invoking expressions such as patent illegality, public policy or shocking the conscience of the Court.

The Court also clarified that an award cannot be partially modified by separating its components when the underlying claims and measurements are legally and practically inseparable. Examining the invoices and measurements afresh would amount to an impermissible reassessment of the merits.

Further, the fact that the award debtor was a Government entity could not justify interference or confer any special protection against an otherwise valid arbitral award.

Final Decision

The Supreme Court set aside the Calcutta High Court Division Bench's judgment and restored the original arbitral award in favour of the contractor.

The decision reinforces the limited scope of judicial interference with arbitral awards and makes clear that the mere magnitude of an award cannot justify its reduction without substantive legal grounds.

Case Details

Case Name: M/s Marino Dredgeco Limited v. The Board of Trustees of the Port of Kolkata

Court: Supreme Court of India

Date of Decision: 18 November 2026

Case Number: Civil Appeal Nos. 14303 and 14304 of 2026

Coram: Justice J.B. Pardiwala and Justice K. Vinod Chandran